Executive Mayor Cllr Samkelo Janda continued his oversight visits to monitor progress on key infrastructure projects currently underway in Willowvale.
- One of the key projects visited was phase one of the Willowvale Taxi Rank, where significant construction activities are in progress.
- Clearing and grubbing
- Construction of water reticulation systems
- Installation of sewer reticulation infrastructure
- Mass earthworks
- Construction of a retaining wall
- Block paving
- Installation of a new septic tank
- Construction of ablution facilities
- Construction of a taxi shelter
- Erection of fencing with gates and Eskom electricity connections
- Installation of a nameboard
- Compliance with all relevant Health & Safety and Environmental Management regulations
- Additional external works
- The Willowvale Removal of Alien Vegetation Project, focuses on removing trees and bushes as part of the Community Services Department’s initiative to enhance local areas within Mbhashe LM.
- Willowvale Landfill Site, aims to stimulate circular economy and promote safer environment in Mbhashe areas.